A 25,000-ton Natural Rubber Production Line in Northeast Thailand

米兰(中国):2019-06-01

Engineering Project :

Production Capacity of 3 ton/hr for natural rubber production line in Thailand

Processing Materials :Natural Rubber,Cup Rubber

Annual Capacity :25Thousand Tons

Finished Product :STR20

Year and Place :2019,Thailand

Matching Heat Source :LPG Furnace

Thailand has been the world's largest producer and exporter of natural rubber since 1991. In 2000, the production of rubber reached 1 million tons, and it is expected to reach 2.4 million tons in 2004. At present, more than 6 million people in the country are engaged in the production, processing and trading of rubber, accounting for nearly one-tenth of the country's population. More than 2 million hectares of rubber are planted.

Pre-breaking Production Line:

Conveyor - Slab Cutter- Vibrating Screen

Drying Rubber Production Line:

Slab Cutter - Single Helix Breaking Crushing Cleaning Machine -Twin Helix Breaking Crushing Cleaning Machine - Creper - Shredder - Creper -Shredder - Drying Line - Packing - Bagging

1. Increase the pre-breaking zone and improve the characteristics of rubber 2. Automatic line 3. Production guaranteed 4. Quality guaranteed 5. Low labor intensity

This production is medium-sized and suitable for companies which are familiar with the rubber industry or need to expand capacity production.The pre-breaking zone is based on local raw materials and the requirements of rubber's characteristic; the two-stage crepe line is suitable for processing all grades of natural rubber raw materials.